Route 131 Paving Project Update - 10/4/13


Work Update
Weathersfield Route 12/131
AOT Project No: STP 2913(1)

Saturday, 10/5/13 – Paving crews will continue paving between Henry Gould Road to Downer’s Corners. Motorists should keep in mind paving will require alternating one-way traffic. Traffic control personnel will be present to assist in maintaining traffic flow.

Week of October 7th, 2013
Traffic Safety Warning – Crews are asking motorists who are exiting driveways or businesses on Route 131 to be aware that they may be pulling into a construction zone. With construction zones taking up to a mile of one lane, a flag person may not be stationed in the exact area to assist someone in pulling out. If there is no flagger present, motorists should wait for traffic flow in the direction they want to go before pulling out.
The construction zone will be marked with orange cones along the centerline.
VT Route 131 – I91 Interchange to Downer’s Corners
Shoulder clean-up work will occur in various areas throughout the project.

Paving – Crews will continue paving the base layer of asphalt between Henry Gould Road and Downer’s Corners throughout the week. This first layer of new pavement is expected to be complete by Tuesday. Paving is contingent upon favorable weather conditions.

Once paving crews reach Downer’s Corners, they will return to the I91 Interchange and start paving the second layer of pavement. They will work West towards Downer’s Corners throughout the remainder of the week.

Please keep in mind there are three layers of new pavement to get installed on this project. Paving is expected to occur for several weeks.

Guardrail – Guardrail crews will return to the project towards the end of the week to adjust guardrail placement along the project.

TRAFFIC DELAYS – ALL operations will require travel to be reduced to alternating one-way travel around the construction packages. Traffic control personnel will be present to assist in maintaining traffic flow. Motorists should anticipate traffic delays while traveling through the project and plan accordingly. Please allow for extra time in your travel plans.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.