Work Update
Weathersfield Route 12/131
AOT Project No: STP 2913(1)
Saturday, 9/21/13 – Crews will be working on Route 131 continuing the cement reclaim, weather permitting, from Jarvis Road to Gulf Road. If it rains and crews cannot continue with the cement reclaiming, they will deliver gravel to the project and reshape the roadway from Gulf Road (west) to Downer’s Corners.
Week of September 23rd, 2013
Traffic Safety Warning – Crews
are asking motorists who are exiting driveways or businesses on Route
131 to be aware that they may be pulling into a construction zone. With
construction zones taking up to a mile of one lane, a flag person may
not be stationed in the exact area to assist someone in pulling out. If
there is no flagger present, motorists should wait for traffic flow in
the direction they want to go before pulling out.
The construction zone will be marked with orange cones along the centerline.
VT Route 12 – I91 Interchange to NH Border
Crews will be working on the traffic signal at the intersection of Route 12 and Route 5.
Guardrail crews will be working in various areas between the I91 interchange and the NH border.
VT Route 131 – I91 Interchange to Downer’s Corners
Crews will be delivering gravel and grading in various areas along
Route 131 throughout the week. Ditching and clean-up work may also occur
throughout the project.
Cement Reclamation – Crews will
continue cement reclaiming the roadway along Route 131 from Gulf Road
(east) to Lottery Lane throughout the week. Similar to the reclaiming of
the existing pavement, cement reclaiming consists of rototilling dry
cement into the existing loose gravel roadway, then rolling the surface
leaving the roadway a packed down gravel surface. Motorists are
encouraged to reduce speed and use caution when driving over the gravel
roadway.
Paving – Crews may start paving the base layer of asphalt
mid-week. They will start at the I91 interchange and work their way West
towards Downer’s Corners. Please keep in mind that the base layer is
the first of three layers of pavement that will be installed. Paving is
expected to occur for several weeks.TRAFFIC DELAYS – ALL operations will require travel to be reduced to alternating one-way travel around the construction packages. Traffic control personnel will be present to assist in maintaining traffic flow. Motorists should anticipate traffic delays while traveling through the project and plan accordingly. Please allow for extra time in your travel plans. Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com. |
Friday, September 20, 2013
Route 131 Paving Project Update - 9/19/13
Subscribe to:
Post Comments (Atom)
No comments:
Post a Comment