Pages

Monday, July 29, 2013

Route 131 Paving Project Update 7/29/13







Work Update
Weathersfield Route 12/131
AOT Project No: 0146(11)

Week of July 29th, 2013
Traffic Safety Warning – Crews are asking motorists who are exiting driveways or businesses on Route 131 to be aware that they may be pulling into a construction zone. With the milling construction zone taking up to a mile of one lane, a flag person may not be stationed in the exact area to assist someone in pulling out. If there is no flagger present, motorists should wait for traffic flow in the direction they want to go before pulling out.
The construction zone will be marked with orange cones along the centerline.

VT Route 131 - I91 Interchange to NH Border
Milling - Monday, crews expect to finish milling between the NH Border and the I91 interchange.
Paving: Tuesday, crews will pave over the milled section of Route 131 between the NH Border and the I91 interchange. Crews will also pave the milled section of Route 5.

VT Route 131 – I91 Interchange to Downer’s Corners
Milling - Tuesday, milling crews will mobilize their operations to approximately Jarvis Road on Route 131 and continue milling towards Downer’s Corners for the remainder of the week.
Excavation Work -
Crews will continue excavation work on Route 131 between the I91 exchange and Jarvis Road.
TRAFFIC DELAYS ALL operations will require alternating one-way traffic around the construction zone. Traffic control personnel will be present to maintain traffic flow. Motorists should anticipate traffic delays while traveling through the project and plan accordingly. Please allow for extra time in your travel plans.

Contact Francine Perkins, Public Relations Officer, FRP Enterprises, LLC with any questions or concerns with regards to the project at 802-479-6994 or for a more up to date schedule visit www.roadworkupdates.com.

No comments:

Post a Comment