Pages

Monday, April 4, 2016

Connecticut River Bridge - Charlestown/Springfield - Rehabilitation Work

NEWS RELEASE
For Immediate Release
March 31, 2016

Contacts:
Rick Oberst, Construction Bureau, 603-933-2024
Bill Boynton, Public Information Office, 603-271-6495
Rehabilitation of Charlestown, NH – Springfield, VT Bridge
NH Route 11 Over the Connecticut River 


The New Hampshire Department of Transportation (NHDOT) announces work is expected to begin mid-April on the rehabilitation of the bridge carrying NH Route 11 over the Connecticut River between Charlestown, New Hampshire and Springfield, Vermont.

This bridge expansion joint replacement work will initially require daytime lane closures and one-way alternating traffic. Two-way traffic will be restored at the close of work daily.

At the completion of the concrete structural work, the bridge will be paved in its entirety. This will require the bridge to be closed to traffic for five days. Advance notice will be given prior to this work.

Miller Construction, of Windsor, Vermont is the contractor for the $695,000 project, which has a final completion date of August 26, 2016.

No comments:

Post a Comment